Time & Work Level-3 Quiz-2

Time & Work Level-3 Quiz-2

Welcome to the Level – 3 Quiz – 2 of the topic Time & Work on Knowvation! The pattern of the quiz will be MCQ and you will encounter many challenging problems which are going to be very helpful for the preparation of various competitive exams like, CAT, IIFT, SNAP, XAT, TISSMAT, TISSNET, CMAT, SSC CGL, etc. You’re requested to please do read the instructions given below before starting this quiz.

Here are some basic instructions:

Time Limit: 20 minutes

Number of Multiple Choice Questions: 10

Passing marks: 70%

You’ll see the answers after you SUBMIT the quiz. ‘Green’ color ticks represents a correct answer and the ‘Red’ ticks represents a wrong answer

Please do provide your valuable feedback on the quiz or report any issue/mistake in the comment box below. ALL THE BEST! 😀

1. A contractor employed some workers to finish a certain project in a specified time. After a few days of work, he realized that the actual time would overshoot the scheduled time by 25%. So, he increased the workforce by a third and managed to finish the project on time. Find the fraction of work that was completed by the time the additional workers were employed.

 
 
 
 

2. In the previous question, What fraction of the scheduled time is the time after which the additional workers were employed?

 
 
 
 

3. A cistern can be filled by two pipes in 8 min and 12 min respectively. Both pipes are opened together for a certain time but due to some defects, only 5/6 th of full quantity of water flows through the former and only 3/4 th through the latter. The defects are detected and rectified. The cistern is filled in 2 min from that moment. How long was it before the defects were rectified?

 
 
 
 

4. A, B and C are three pipes which are attached to a tank. A and B fill the tank in 20 and 30 mins respectively and C empties it in 15 min. If A, B, C are opened in that order for 2 min each till the tank gets filled, then how many minutes will it take for the tank to get filled?

 
 
 
 

5.

In a factory, there are two machines  and  producing toys. They respectively produce  and  units in one hour.  can run a maximum of  hours and  a maximum of  hours a day. The cost of their running per hour respectively amounts to  and  rupees. The total duration of working these machines cannot exceed  hours a day. If the total cost cannot exceed Rs.  per day and the total daily production is at least  units, then formulate the problem mathematically.

 
 
 
 

6. A contractor employed 20 men to complete a project in 50 days. After 30 days, he observed that only 50% of the work had been completed. How many more men should be employed to complete the work in time?

 
 
 
 

7. In the previous question, If the work is increased by 20% of the original and still the contractor wants to finish it within 50 days, then atleast how many more men need to be employed?

 
 
 
 

8. A garrison had provisions for 1500 men for 30 days. After some days, 300 more men joined the garrison. The provisions lasted for a total of 26 days from the beginning. After how many days did the new men join?

 
 
 
 

9. A task is assigned to a group of twenty men, not all of whom have the same capacity to work. Every day exactly two men out of the group work on the task, with no same pair of men working together twice. Even after all the possible pairs have worked once, all the men together had to work for exactly one more day to finish the task. Find the number of days required for all the men working together to finish the task.

 
 
 
 

10.

Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48 days, respectively. Amar, Bhavan and Chetan started it. After 6 days, Amar left. The other two continued to work. Bhava left 15 days before the completion of the job. Chetan complete the remaining work. Find the total time taken to complete the job . ( in days)
 
 
 
 